We’re operating based on the following schedule. The timetable and execution may be influenced by political decisions and the permitting processes required for port operations and expansions.

Current permit issues

• Zoning plans (Norrköping Municipality)
• Water permits (Norrköping Municipality)
• Operating permits (Norrköpings Hamn AB)
• Building permits

2023-2025

• Dismantling and reconstruction of Quay P8 with integrated section for heavy goods
Completion of construction works at the Pampus Terminal
Commissioning of the new quay and port area

2021-2022

Contractor work on the quay and port area begins
• Electrical system and other contractor work commences

2020

Completion of dredging contractor works
• Initiation of contractor works for quay and port area
• Preparation of specifications for electrical systems

2019

New port area at the Brick Warehouse, Öhman Terminal
• Procurement of pre-construction and dredging contracts
• Pre-construction contractor works at the Pampus Terminal
• Commencement of dredging contractor works

2018

Environmental permit for water operations at the Pampus Terminal
• Conclusion of contractor works at the Öhman Terminal
• Preparation of specifications for the expansion of the Pampus Terminal

2017

Norrköping Municipality submits permit application for environmental approval, water operations at the Pampus Terminal
• Contractor works at the Öhman Terminal
• Ongoing work on system documentation for the expansion of the Pampus Terminal

• Commencement of construction for the Kardon Track

2016

• Vacating the Northern quay in the Inner Harbor.
• Initiating the permit application for environmental approval, and water operations for the expansion of the Pampus Terminal.
• Decision-making regarding the extent of expansion at the Pampus Terminal and Öhman Terminal.
• Establishing system documentation for the planned expansion at the Pampus Terminal.
• Detailed designing of planned actions at the Öhman Terminal.
• Detailed planning of the Kardon Track project.